Friday, April 20, 2012 at 12:22PM SITE WORK HAS BEGUN!
Welcome to the BFMS Renovation Project!
We hope you'll take a look around, as there is a lot of great information on the project. Details of all Renovation Design Committee meetings (summer of 2011 through spring of 2012) can be found on the minutes page.
PROJECT NEWS
The Renovations are underway! Work has begun on the ground floor and site work in the front of the building. After April break, the gymnasium will no longer be in use. Students will be bussed to Hadley Field for P.E. classes.
The "Working Committee" is meeting weekly with the contractor and architect during construction. Members of the working committee are Chris Kibbe, Heidi Moccia, Rich Schuhmann, a representative appointed by the school board, and our clerk of the works, Scott McKusick. The School Board has also created a Project Advisory Committee which will meet monthly to address any specific issues referred to it by the School Board, and to help keep open the lines of communication with the Rockingham community during the construction process.
Below is a brief overview of the estimated construction schedule:
- Spring 2012 - June 2012: Construction begins on the ground floor! (demolotion of old locker rooms and begin construction of hallway to elevator), and site work.
- Summer 2012: Site work, Ground Floor, Second Floor, Third Floor, and Heating and Ventillation Systems.
- Sept. 2012 - June 2013: First Floor Classrooms.
- Summer 2013. Cafeteria and Kitchen.
Thank you for visiting and please visit again.